OUR ENERGY PROJECTS

We want to create energy projects with added value

Our energy projects aim to increase the availability of renewable energy sources in Denmark. We collaborate with the local community and municipalities to implement energy plants in suitable locations for the benefit of the green transition. 

The goal of the energy projects is to reduce our society's dependence on fossil energy and contribute to a sustainable future, where renewable energy is the norm and the primary energy source.

Below you will find a list of selected projects and their current status. 

Municipality:
Hedensted

Gross area:
140 ha

Status:
Politically prioritized on March 6, 2023 in the application round. Awaiting political decision to initiate local plan process.

Municipality:
Aabenraa

Gross area:
72 ha

Status:

Politically prioritized
on 5 September 2023 in the application round.
Awaiting political decision to initiate the local plan process.

Municipality:
Favrskov

Gross area:
300 ha

Status:Politically prioritized on 31 January 2023 in the application round. Awaiting completion of the idea consultation on March 7, 2024, and then initiation of the local plan process.

Municipality:
Tønder

Gross area:
125 ha


Status:

Local plan process initiated on July 7, 2023. 

Municipality:
Esbjerg

Gross area:
35 ha

Status:
Politically prioritized on 20 November 2023 in the application round. Awaiting political decision to initiate local plan process.

Municipality:
Middelfart

Gross area: 175 ha

Status: Politically prioritized on 8 April 2024, awaiting political decision to initiate the local plan process.

Municipality:
Tønder

Gross area:
69 ha

Status:
Local plan process initiated on July 7, 2023 .

Municipality:
Varde

Gross area:
15/175

Status:

Politically prioritized on 13 October 2022 in the application round. Awaiting political decision to initiate local plan process.

Municipality:
Holstebro

Gross area:
160 ha

Status:

Politically prioritized on 29 August 2023 in the application round. Awaiting political decision to initiate local plan process.

Municipality:
Hedensted

Gross area:
52 ha

Status:

Local plan process is ongoing. Final local plan expected Q1 2024.

Municipality:
Odder

Gross area:
35/90 ha

Status:

Local plan process is ongoing. Final local plan expected Q2 2024. 

Read more about UNISON below

UNISON Energy Partners is a Danish company developing, building, and operating renewable energy projects. We want to be the trusted partner in renewable energy, helping companies and society on the way to a green transition.

Read more about who UNISON is here:

We want to help other companies and society with achieving their objectives within sustainability. Thereby we can leave a significant mark on the transition to a future where renewable energy production is the norm.

Read more about how we work here:

At UNISON, we ensure to adapt the energy project to the surrounding nature. With our initiatives promoting biodiversity, we want our energy projects to create the best conditions in and around the project area, where flora and fauna can unfold.

Read more about our approach here: