April 7 - June 2, 2025
Consultation of planning basis and environmental assessment

The planning basis and environmental assessment are in public consultation. Documents can be accessed via Tønder Municipality's website here.

March 2025
Political treatment

The planning basis and environmental assessment are processed politically through three committee meetings and a municipal council meeting

April 2024 - February 2025
Preparation of planning basis and environmental assessment

Planning basis and environmental assessment are prepared

May 2024 - June 2024
Consultation of scoping memo

The scoping note for environmental assessment is in public consultation

November 2023
Resume dialogue with immediate neighbors
August 2023
Consultation of ideas

Call for ideas and suggestions for the project

December 2022
Second application submitted to Tønder Municipality

Submission of application for the establishment of a solar cell plant at Ballum Hede in connection with application round

August 2022
Political treatment

The municipal council decided not to proceed with this project

June 2022
Dialogue meeting with local citizens

Ideas and suggestions for developing recreational activities in and around the project area

February 2022
Information meeting

Information meeting held in Ballum Multihus

December 2021
First application submitted to Tønder Municipality

Submission of application for the establishment of a solar cell plant at Ballum Hede in connection with application round

fall 2021
Engaging with neighbors and communities
Summer 2021
Identification of project area and initial dialog with landowners