Energy Park Sindbjerg
Welcome to the info page for Energipark Sindbjerg

This page shows the latest status of the project. The development of a renewable energy project is a dynamic process where changes can occur continuously, partly based on local and municipal dialog. Therefore, project-specific information may change during the development and planning process.
Below Timeline and Status you can see the latest updates on the project.
About the project
The total gross area of the project is approximately 157 hectares. Of this, the area for solar cells is approximately 137 hectares. The project area is located in open country south of the community Vester Ørum and north of Lindved, by the Midtjyske Motorway.
The project includes a ground-mounted photovoltaic system, wind turbines and BESS. The solar modules are expected to produce approximately 178.5 million kWh/year. The wind turbines are expected to produce approximately 38.5 million kWh/year. The total production of the energy park is thus expected to be approximately 217 million kWh/year.
When delimiting the area, it has been emphasized that the facility constitutes a single unit and that distance to neighbors located in the immediate vicinity of the project area is ensured.
Greater consistency and accessibility
This is the preliminary layout plan of the project. The layout plan shows the different elements within the project area. The layout plan has been prepared based on local input, municipal dialog and consideration for the internal and surrounding nature and environment.
Gross area
approx. 157 ha
Production
approx. 217,000 MWh
solarAREAL
approx. 137 ha
Path
approx. 6.5 KM
area kept free
approx. 18 ha
Visualizations
A series of preliminary visualizations of the project have been made from five photo points in the area.
The photos were taken with a focal length of 35 mm and the photo points are shown on the map here.
The installation is visualized with 3.5 meter high south-facing panels and surrounding vegetation of 4 meters.
NOTE: The visualizations were made at an early stage of the project development. Since then, the wind turbines have been relocated to the west. However, the visualizations below still give a true picture of the landscape when the project is established. The visualizations will be updated during the planning process.
Possible inner planting belts and passages through the facility are not visualized.

Photo point 1
From Skanderborgvej towards northwest


Photo point 2
From Skanderborgvej (near Vester Ørum)


Photo point 3
Near Sechersvej in Vester Ørum to the south


Photo point 4
From Ribevej towards southeast


Photo point 5
Near Engelgårdsvej to the east